Plan showing where excavation is to begin and how it will proceed around the site.
-
Soldier piles are placed in augured shafts.
-
Excavation begins. Clean and contaminated soil are segregated.
-
Lagging is installed.
-
Excavation continues.
-
Tie-backs are installed.
-
Excavation continues to full depth.
-
Contaminated soil is trucked off site.
-
Clean soil is used to backfill hole.
-
Work continues in a similar fashion around the site.
-