Plan showing where excavation is to begin and how it will proceed around the site.
Soldier piles are placed in augured shafts.
Excavation begins. Clean and contaminated soil are segregated.
Lagging is installed.
Excavation continues.
Tie-backs are installed.
Excavation continues to full depth.
Contaminated soil is trucked off site.
Clean soil is used to backfill hole.
Work continues in a similar fashion around the site.